Analysis of Risk Factors for Delays in the Implementation of the Meninting Dam Construction Project, West Lombok Regency

Authors

  • Auliya Isoihati Mataram Civil Engineering Department, University of Mataram
  • Yusron Saadi Mataram Civil Engineering Department, University of Mataram
  • Suryawan Murtiadi Mataram Civil Engineering Department, University of Mataram

DOI:

https://doi.org/10.31305/rrijm.2024.v09.n07.017

Keywords:

Delays, Meninting Dam, FTA, PIM, Residual Risk, Response

Abstract

The Meninting Dam Construction Project is part of the National Strategic Project (PSN). Delays can occur in any project, including the construction of the Meninting Dam in West Lombok. This study aims to identify and analyze risk factors impacting the project, determine the risks classified as dominant major risks, and evaluate the residual risks of the Meninting Dam construction project to formulate risk responses that minimize the impact on the project. The study employs the Fault Tree Analysis (FTA) and Probability Impact Matrix (PIM) methods and uses related sources as theoretical foundations. Based on the study results, the Meninting Dam project identified four factors that most significantly affect delays using the FTA method: 1) “Delay in decision-making by the owner,” probability = 17.443%, 2) “Lack of control over work by Construction Management,” probability = 13.771%, 3) “Inadequate planning and control by the Contractor,” probability = 17.207%, and 4) “Weather intensity or high rainfall/heat,” probability = 13.041%. From the identification, four dominant risk variables with high risk levels were obtained using the PIM method: 1) Objections from local residents regarding land acquisition, 2) Delays in material arrival, 3) Delays in procurement of work equipment, and 4) High rainfall causing uncompact soil to become landslides. The risk mitigation category used in this study is risk reduction. The assessment of residual risk shows that of the four risks initially at a high level, these risks decreased after risk mitigation, with two risks becoming moderate and two risks becoming low.

References

Aftortu, M. R., Kustiani, I. dan Siregar, A. M. (2019). “Analisis Risiko Proyek Konstruksi Studi Kasus Bendungan Way Sekampung Paket 2 Dengan Metode Failure Mode and Effect Analysis dan Domino”, JRSDD, Vol. 7, No. 1, hal. 549-558.

Agritama, P. R., Huda, M. dan Rini, S. T. (2018). “Faktor–faktor yang mempengaruhi keterlambatan proyek Konstruksi di Surabaya”, Jurnal Rekayasa dan Manajemen Konstruksi, Vol 6 No.1, Hal 25-32.

Al-Bahar, J. F. dan Crandall, K.C. (1990). “Systematic Risk Management Approach for Construction Projects”, Journal of Construction Engineering and Management, 116 (3), 533-546.

Amalia, R. (2012). “Analisis Penyebab Keterlambatan Proyek Pembangunan Sidoarjo Town Square”, Jurnal Teknik ITS, Vol. 1 No. 1, ISSN : 2301- 9271.

AS/NZS 4360:60. (2004). “Risk Management Guidelines”. Standards Australia International Ltd, Sydney.

Assaf, S. A., dan Al-Hejji, S. (2006). “Causes of delay in large construction projects, International Journal of Project Management”, 24(4), 349-57.

Astina, D. C. (2012). “Analisis Faktor-Faktor Penyebab Keterlambatan Pelaksanaan Pekerjaan Proyek Konstruksi di Kabupaten Tabanan”, Jurnal Ilmiah Elektronik Infrastruktur Sipil, Denpasar.

Australian/New Zealand Standard. 2004. AS/NZS 4360, Risk Management Standard. Australia.

Ayub, A., Aslam, M. S., Razzaq, A., dan Iftekhar, H. (2013). A Conceptual Framework On Evaluating SWOT Analysis. European Journal of Business and Social Sciences, Vol. 2(1), pp. 91–98, Retrieved from http://www.ejbss.com/recent. Aspx.

Barrie, D. S., dan Paulson, B. C. (1984). Professional Construction Management. McGraw-Hill, Inc., New York.

Bhavsar, U. M., dan Solanki, J. V. (2020), “Identification Of Constraints In Construction Projects”, International Research Journal of Engineering and Technology, Vol. 07, hal. 6302-6307.

Carlson, C. (2012). “Effective FMEAs : Achieving safe, reliable, and economical products and processes using failure mode and effect analysis”. Canada: United Stated of America.

Clemens, P. (1993). Fault Tree Analysis, fourth edition, Jacobs Sverdrup, George Washington University.

Dewi, A. I. (2013). “Analisis Risiko Pada Proyek Pembangunan Underpass Di Simpang Dewa Ruci Kuta Bali”, Jurnal Teknik Pomits Vol. 2, No. 2.

Ericson, C. A. (2005). Hazard Analysis Techniques for System Safety. Hoboken, New Jersey: John Wiley & Sons, Inc.

Faridi, A., dan El-Sayegh, S. (2006). “Significant factors causing delay in the UAE construction industry”, Construction Management and Economics, 24: 11, 1167 — 1176.

Haseeb, M. Lu, X. dan Bibi, A. (2011). “Problems of Projects and Effects of Delays in the Construction Industry of Pakistan”. Australian Journal of Business and Man-Accounting and Management Journal, Vol. 2, No. 1, July 2018.

Heldman, K. (2005). Project Manager’s Spotlight on Risk Management, Harbor Light Press, Alameda.

Isnaini, R. (2011). Analisis Dan Respon Risiko Pada Proyek Pembangunan Galangan Kapal Kabupaten Lamongan, Tugas Akhir, Institut Teknologi Sepuluh Nopember, Surabaya.

Joni, I. G. (2012). Risiko manajemen Proyek. Jurnal Ilmiah Teknik Sipil, 16.

Kementerian Pekerjaan Umum dan Perumahan Rakyat. (2021). “Data Bendungan di Indonesia tahun 2021”. Bina Operasi dan Pemeliharaan Direktorat Jenderal Sumber Daya Air (Database DWH).

Kerzner, H. (2009). Project Management Tenth Edition. Hoboken, New Jersey: John Wiley & Sons, Inc.

Kesuma, P. A. (2019). “Analisa Risiko Kemacetan Jalan Raya Akibat Problem Pada Kendaraan Berat”, Tesis, Institut Teknologi Sepuluh Nopember, Surabaya.

Kurniawan, B. Y. (2011). Analisa Risiko Konstruksi pada Proyek Pembangunan Apartemen Petra Square Surabaya, Tugas Akhir, Institut Teknologi Sepuluh Nopember, Surabaya.

Kurniawan. R. (2015). “Studi Keterlambatan Proyek Pembangunan Kapal Kargo dengan Metode Bow Tie Analysis”. Tugas Akhir - MO 141326, Institut Teknologi Sepuluh Nopember, Surabaya.

Kocecioglu, D. (1991). Reliability Engineering Handbook. Englewood Cliffs, Prentice-Hall. Volume 2.

Levitt, R. E., Ashley, D. B. dan Logcher, R. D. (1980). “Allocating Risk and Incentive in Construction.”Journal of the Construction Division. ASCE. 106(CO3).

Lim, T. E., dan Niem, B. C. (1995). “Quality Management System”. Volume 2. Assessment to ISO 9000:1994 series, Singapore.

Megasari, A. (2005). Modul Mata Kuliah Teknik Evaluasi Bahaya (Manajemen Risiko). Surabaya: Program Studi D4 Teknik Keselamatan dan Kesehatan Kerja PPNS-ITS.

Modarres, M. (1999). Reliability Engineering and Risk Analysis. Marcel Dekker Inc, New York.

Monahan, G. (2008). Enterprise Risk Management A Methodology for Achieving Strategic Objectives.

Mustika, A. F. (2014). Analisis Keterlambatan proyek menggunakan Faulth Tree Analysis (FTA). Tugas Akhir S1-Teknik Sipil, Universitas Brawijaya, Malang.

PMI. (2013). A Guide to the Project Management Body of Knowledge, Fifth Edition. Newtown Square, Pennsylvania: Project Management Institute, Inc.

Pranomo, S. R. (2022). Analisis Risiko Pelaksanaan Kerja Sama Operasi .

Priyanta, D. (2000). Keandalan dan Perawatan, Institut Teknologi Sepuluh Nopember. Surabaya. Putra, A.T. (2014). Evaluasi Keterlambatan Pada Proyek Pembangunan Jacket Structure : Studi Kasus Proyek EPCC Bukit Tua PT.PAL Indonesia, Tugas Akhir S1-Teknik Kelautan, Institut Teknologi Sepuluh Nopember, Surabaya.

Putra, B. F. (2018). ”Analisis Faktor Penyebab dan Mitigasi Waste pada Proyek Konstruksi Gedung di Kota Surabaya”. Tesis, Institut Teknologi Sepuluh Nopember, Surabaya.

Ratnaningsih, A., dan Pangapuri, D. G. A. (2014). Analisis Risiko Manajemen Konstruksi Pembangunan Waduk Bajulmati Banyuwangi - Jawa Timur. Seminar Nasional X Inovasi Struktur dalam Menunjang Konektivitas Pulau di Indonesia, ISBN 978-979-99327-9-2.

Rifai, W. (2018). Analisis Risiko Keterlambatan Pelaksanaan Konstruksi Proyek Spazio Tower 2 Surabaya, Tesis, Institut Teknologi Sepuluh Nopember, Surabaya.

Rosdianto, M. A. (2017). Analisa Risiko Keterlambatan Proyek Pembangunan Apartemen Di Apartemen Taman Melati Surabaya, Tesis, Institut Teknologi Sepuluh Nopember, Surabaya.

Royal Society. (1991). Reports of the Study Group on Risk: Analysis, Perception, and Management, London: (group co-ordinator Sir F. Warner), Royal Society

Saaty, T. (1993). Pengambilan Keputusan Bagi Para Pemimpin, Proses Hirarki Analitik untuk Pengambilan Keputusan dalam Situasi yang Kompleks. Pustaka Binama Pressindo.

Sakishk, R. Y. (2017). Analisa Faktor Penyebab Keterlambatan Penyelesaian Proyek pembangunan Mall ABC, Tesis, Institut Teknologi Sepuluh Nopember, Surabaya.

Smith, R. G. dan Bohn, C. M. (1999). ”Small to Medium Contractor Contingency and Assumtion of Risk.” Journal of Construction Engineering

Sugiyono. (2007). “Statistika untuk Penelitian”. Jawa Barat: Alfabeta.

Umar, H. (1998). Riset Sumberdaya Manusia dalam Organisasi. Jakarta: PT. Gramedia Pustaka Utama.

Downloads

Published

15-07-2024

How to Cite

Isoihati, A., Saadi, Y., & Murtiadi, S. (2024). Analysis of Risk Factors for Delays in the Implementation of the Meninting Dam Construction Project, West Lombok Regency . RESEARCH REVIEW International Journal of Multidisciplinary, 9(7), 128–140. https://doi.org/10.31305/rrijm.2024.v09.n07.017

Most read articles by the same author(s)